Our Work
Pharmaceutical Manufacturing Facility in Bristol, TN
S. B. White Company was chosen to install and hookup quite a large unit for a local pharmaceutical manufacturing facility in Bristol. They had an extremely aggressive schedule of thirty days to complete the installation of 1,240 feet of 6″ welded steel chill water lines and 780 feet of 42″ diameter spiral sheet metal ductwork across the roof. We bid the job knowing that we would find out if we were successful or not within days and would have to order material and be ready to start in a matter of two weeks and finish in 30 days. We met the aggressive schedule and actually beat it on the piping installation. It turned out to be a slick installation and a good project for both the owner and ourselves.